Integrated Kashang HEP (IKHEP) envisages development of Kashang and Kerang Streams, tributaries of the river Sutlej comprising four distinct stages as under:
Stage-I (65 MW):
Comprising diversion of the Kashang stream, at El.2829 m, to an underground powerhouse located on the right bank of Satluj near Powari Village, developing a head of approximately 830 m. On 01.09.2016, IKHEP’s one unit of 65 MW has been successfully commissioned.
Stage-II & III (130 MW):
Comprising diversion of the Kerang stream, at El. 2872 m, into an underground water conductor system leading to upstream end of Stage-I water conductor system, augmenting the generating capacity of Stage-I powerhouse, using Kerang waters over the 820 m head available in Kashang Stage-I powerhouse.
Stage-IV (48 MW):
This stage is more or less independent scheme harnessing the power potential of Kerang stream upstream of the diversion site of Stage-II. In this scheme, a head of approximately 300 m could be utilized to develop power in an underground powerhouse located on the right bank of Kerang stream.
Kashang HEP Stage-I (65 MW):
Capacity |
65 MW |
Design Energy (in 90% dependable year) |
245.8 MU |
Design Head |
821 Meter |
Diversion Structure |
Weir, 15 m (L), 2.20 m (W) |
Head Race Tunnel |
1994.325 m long, D- Shaped with 3.50 x 4.115m. |
Penstock/Pressure shaft |
Steel lined (Underground), Circular Shape |
Power House |
1 No. vertical axis Pelton turbine with generating units of 65 MW. |
Kashang HEP Stage-II & III (130 MW):
Capacity |
130 MW |
Design Energy (in 90% dependable year) |
544.83 MU |
Net Head |
821 m |
Diversion Structure |
Trench Weir |
KK Link Tunnel |
6300 m long, D- Shaped with 3.50 x 4.5m. |
Penstock/Pressure shaft |
Steel lined (Underground), Circular Shape |
Power House |
2 No. vertical axis Pelton turbines with generating units of 65 MW each. |
Kashang HEP Stage-I (65 MW):
Village |
Power house near Powari Village |
Tehsil |
Kalpa |
District |
Kinnaur |
State |
Himachal Pradesh |
Kashang HEP Stage-II & III (130 MW):
Village |
Power house near Powari Village |
Tehsil |
Kalpa |
District |
Kinnaur |
State |
Himachal Pradesh |
Kashang HEP Stage-IV (48 MW):
District |
Kinnaur |
State |
Himachal Pradesh |