Hydro Power

HPPCL has successfully commissioned its 1st hydro electric project on 01.09.2016. Presently, it is having an Installed Capacity of 276 MW from its 03 Hydro Power Stations and is engaged in the construction of 02 hydro projects aggregating to a total capacity of 580 MW.

One Multipurpose Project (660 MW) is also being developed by HPPCL in joint venture with Govt. of Uttarakhand.

HPPCL’s Hydro Electric Projects:

Commissioned Projects (276 MW)

S.No. Project Name Basin River/Tributary Location Installed Capacity Unit Size COD
1 Kashang HEP Stage-I Satluj Kashang Khad Kinnaur, HP 65 MW 1X65 MW Unit-1- 01.09.2016
2 Sainj HEP Beas Beas Kullu, HP 100 MW 2X50 MW Unit-1 & 2- 04.09.2017
3 Sawra Kuddu HEP Yamuna Pabbar Shimla, HP 111 MW 3X37W Unit-1,2 & 3-21.01.2021

Under Construction (628MW)

S.No. Project Name Basin River/ Tributary Location Installed Capacity Unit Size
1 Shongtong Karcham HEP Satluj Satluj Kinnaur, HP 450 MW 3X150 MW
2 Kashang Stage-II & III Satluj Kashang & Kerang Khad Kinnaur, HP 130 MW 2X65 MW
3 Chanju -III HEP Ravi Chanju Nallah/ Mahed Nallah Chamba, HP 48 MW 2X24MW

Under Investigation & Pre-Const. Clearances Stage ( 1325 MW)

S.No. Project Name Basin River/ Tributary Location Installed Capacity
1 Renukaji Dam Project Yamuna Giri Sirmaur, HP 40 MW
2 Deothal Chanju HEP Ravi Deothal Nallah Chamba, HP 30 MW
3 Thana-Plaun HEP Beas Beas Mandi, HP 191 MW
4 Nakthan HEP Beas Parbati, Tosh Kullu, HP 460 MW
5 Surgani Sundla HEP Ravi Siul Chamba, HP 48 MW
6 Gyspa Dam Project Chenab Bhaga Lahaul & Spiti, HP 300 MW
7 Chirgaon- Majhgaon HEP Yamuna Pabbar Shimla, HP 60 MW
8 Dhamwari Sunda HEP Yamuna Pabbar Shimla, HP 70 MW
9 Triveni Mahadev HEP Beas Beas Hamirpur, HP 78 MW
10 Kashang Stage IV Satluj Kerang Khad Kinnaur, HP 48 MW

Projects Under Prefeasibility Stage (927 MW)

S.No. Project Name Basin River/ Tributary Location Installed Capacity
1 Lujai HEP Chenab Lujai Nallah Chamba, HP 45 MW
2 Chiroti Saichu HEP Chenab Saichu Nallah Chamba, HP 26 MW
3 Saichu Sach Khas Chenab Saichu Nallah Chamba, HP 117 MW
4 Saichu HEP Chenab Saichu Nallah Chamba, HP 58 MW
5 Khab HEP Satluj Khab Kinnaur, HP 636 MW
6 Bara Khamba HEP Satluj Sorang Nallah Kinnaur, HP 45 MW

Project(s) Under Joint Venture (With Govt. of Uttarakhand)

S.No. Project Name Basin River/Tributary Location Installed Capacity
1 Kishau Multipurpose Project Yamuna Tons Sirmaur (H.P), Dehradun (Uttrakhand) 660 MW

 

Last Updated On 24/03/2023